The wetroom tiling is complete... |
Just when it looked as though things were slowing down, there now seems to be a bright light at the end of the tunnel. The building work on our loft conversion project must surely be coming to an end soon.
On Friday and Saturday, the brickie finished the gabling work, which means the plumbers can now come in and install the fixtures for the wetroom.
The week began with a team boarding an area inside the eves, behind the small door in the closet, which meant the brickie was free to fill the enormous hole in the side of our house.
The week began with a team boarding an area inside the eves, behind the small door in the closet, which meant the brickie was free to fill the enormous hole in the side of our house.
Elsewhere, Rachel has organised several tradesmen to come in, to give us quotes for both laying new carpet (in the loft area, down the stairs and into the lounge) and installing a new first floor bathroom (the current incumbent having suffered somewhat during all the works elsewhere).
It's all coming together!
No comments:
Post a Comment
Thank you for your interest in HeroPress.
Comment moderation is currently on again because of annoying spammers!
My apologies to genuine commentators for the inconvenience.
As ever I shall endeavour to acknowledge, and respond to, your comments ASAP.
However, if you're just looking to post spam, please don't bother. It's neither big nor clever. And will just be deleted.